What description best represents Capabilities as defined in SAFe?

  • A . Capabilities are simply a level of abstraction above Epics, exhibiting largely the same characteristics and practices.
  • B . Capability is a different name for Features, one that is preferred by some organizations.
  • C . Capabilities are simply a different kind of Epic, exhibiting largely the same characteristics and practices.
  • D . Capabilities are simply a level or abstraction above Features, exhibiting largely the same characteristics and practices.

Show Answer Hide Answer

Suggested Answer: D

   
ReplyQuote
(@valencesar)
Estimable Member
Joined: 2 months ago
Posts: 122
 

What activity calls for using ROAM technique?

  • A . Refining the Program Backlog.
  • B . Managing the ART sync.
  • C . Categorizing program risks during PI Planning.
  • D . Managing teams by the Release Train Engineer.

Show Answer Hide Answer

Suggested Answer: C

   
ReplyQuote
 Pete
(@spurgerspete)
Estimable Member
Joined: 2 months ago
Posts: 131
 

(Select 2) Why is Architectural Runway important?

  • A . It supports a stable velocity.
  • B . It provides the documentation on which Features and Capabilities are built.
  • C . It iteratively evolves the architecture to meet changing needs.
  • D . It allows for nontechnical changes

Show Answer Hide Answer

Suggested Answer: A, C

   
ReplyQuote
(@rusconilance)
Estimable Member
Joined: 2 months ago
Posts: 130
 

What is the most effective way to train the System Team members to operate effectively as part of the train?

  • A . Have them attend Leading SAFe training and Scrum Master orientation.
  • B . Have them attend Leading SAFe training.
  • C . Have them attend SAFe for Teams training with all other teams on the train.
  • D . Have them attend Implementing SAFe training with SPC certification.
  • E . Have them review the SAFe Foundations presentation and provide on-the-job training.

Show Answer Hide Answer

Suggested Answer: C

   
ReplyQuote
 Ed
(@meriweathered)
Estimable Member
Joined: 3 months ago
Posts: 123
 

What are the primary responsibilities of Program Portfolio Management (PPM)?

  • A . Governance, strategy and investment funding, program management.
  • B . Program management, stakeholder management, PI Planning.
  • C . Lightweight business case, Epic specification workshop, Budget allocation.
  • D . Governance, investment funding, product strategy.

Show Answer Hide Answer

Suggested Answer: A

   
ReplyQuote
 Kim
(@genslerkim)
Estimable Member
Joined: 2 months ago
Posts: 116
 

What role would a traditional program manager most likely take on in SAFe?

  • A . Release Train Engineer or Value Stream Engineer.
  • B . Scrum master
  • C . Business Owner
  • D . Product Manager

Show Answer Hide Answer

Suggested Answer: A

   
ReplyQuote
(@seekellclaud)
Estimable Member
Joined: 2 months ago
Posts: 133
 

What activity occurs during the program Inspect and Adapt workshop?

  • A . PI Predictability Measure update.
  • B . Roadmap update
  • C . Team Iteration Demo
  • D . Biweekly System Demo
  • E . Iteration Metrics update

Show Answer Hide Answer

Suggested Answer: A

   
ReplyQuote
(@kirschkasey)
Estimable Member
Joined: 3 months ago
Posts: 121
 

In SAFe, who owns the Vision for a PI?

  • A . Product Owner
  • B . Business Owners
  • C . Scrum Master
  • D . COE
  • E . Product Management

Show Answer Hide Answer

Suggested Answer: B

   
ReplyQuote
(@oreskovichhayden)
Estimable Member
Joined: 2 months ago
Posts: 133
 

What are stretch objectives?

  • A . Objectives that are beyond the capacity of the team and so are uncommitted for the PI.
  • B . Objectives that are part of the team's capacity but not necessarily achievable during the PI.
  • C . Objectives that are identified during the PI.
  • D . Objectives that the business has promised to their Customers.

Show Answer Hide Answer

Suggested Answer: B

   
ReplyQuote
(@rodenboughdenis)
Estimable Member
Joined: 3 months ago
Posts: 107
 

(Select 2) What would you examine when identifying Value Streams in an enterprise moving to SAFe?

  • A . The project cost accounting procedures in place.
  • B . The internal departments which are supported.
  • C . The number of ARTs which would be contained in the Portfolio.
  • D . The current products which the company sells.

Show Answer Hide Answer

Suggested Answer: B, D

   
ReplyQuote
(@regansnumbers)
Estimable Member
Joined: 3 months ago
Posts: 134
 

The portfolio Vision is an aggregation of every Agile Release Train's Vision?

  • A . True
  • B . False

Show Answer Hide Answer

Suggested Answer: B

   
ReplyQuote
(@rankehaywood)
Estimable Member
Joined: 2 months ago
Posts: 130
 

(Select 2) What applies to the Portfolio Backlog?

  • A . The Portfolio Kanban holds Capabilities that are ready for implementation.
  • B . Programs plan PIs so that they exhaust the Portfolio Backlog and only then work on their local priorities.
  • C . It provides a low-cost holding area for approved Business and Enabler Epics.
  • D . WSJF is used to prioritize Epics in the Portfolio Backlog.

Show Answer Hide Answer

Suggested Answer: C, D

   
ReplyQuote
(@zetobenito)
Estimable Member
Joined: 2 months ago
Posts: 140
 

When does the System Demo happen?

  • A . After the Solution Demo, but before PI Planning.
  • B . After every Iteration.
  • C . On demand.
  • D . After continuous integration.
  • E . After Pre-PI Planning.

Show Answer Hide Answer

Suggested Answer: B

   
ReplyQuote
 Yong
(@deblieckyong)
Estimable Member
Joined: 3 months ago
Posts: 119
 

Test automation is typically included in the Definition of Done (DoD).

  • A . True
  • B . False

Show Answer Hide Answer

Suggested Answer: B

   